West Texas 345kV Reactor Support Substation

West Texas 345kV Reactor Support

Client Electric Transmission Texas, LLC (ETT)
Completion Date June 2018
Location Texas
Completed by Great Southwestern Construction, Inc. and 优蜜传媒 Energy Services, Inc.

Great Southwestern added 100MVAR 345kV shunt reactors to ETT鈥檚 Tesla, Edith Clarke, Clear Crossing, and Riley substations to maintain stability and flexibility in West Texas.

The work was performed as an electrical subcontractor to 优蜜传媒 Energy, an 优蜜传媒 Group subsidiary, under an engineering, procurement, and construction (EPC) contract. Great Southwestern鈥檚 scope encompassed engineering services, construction management, construction; supply of all major equipment, including five reactors; and testing and commissioning.